Fairfield, James Bay, Oak Bay South, Fernwood and Rockland are full of houses built in the early 1900s. Homes wired before about 1950 typically used knob-and-tube.
Knob-and-tube (K&T) runs the hot and neutral as separate wires on ceramic knobs along the joists, and through ceramic tubes where they cross framing. It met code and was safe when it went in. Many insurers won't cover it now.
Why insurers push back
1. It can't handle modern loads
K&T was sized for a 1920s house: a few lights, a radio, an iron, later a fridge. The wire is 14-gauge with rubber-and-cloth insulation rated for 60°C. Run a space heater on it and the wire heats up, and that insulation is now 80–110 years old.
2. Attic insulation
Many older Victoria homes have had attic insulation added since the 1970s, often right over the K&T. The wiring was designed to shed heat into open air. Buried in cellulose or batt, it runs hot until the wire's insulation breaks down and the copper is bare.
3. No ground
K&T has no equipment grounding conductor, so every outlet on it is ungrounded. It also makes it harder to add GFCI and AFCI protection properly, and BCEC 2024 expands where AFCI and GFCI protection is required.
Many insurers won't cover knob-and-tube, or want a written commitment to rewire, often within 6–12 months.
Got a renewal notice or an inspection flag?
A written rewire quote from a licensed contractor is often enough to satisfy your insurer or buyer for now. Book a K&T assessment →
How to tell if you have it
If your Greater Victoria house was built before 1950, assume it has K&T until someone checks. Many pre-1950 homes in Fairfield, James Bay, Rockland and Oak Bay South still have some, mostly in the attic and the second-floor bedroom walls.
- White ceramic knobs. About the size of a wide thumb, along attic joists or rafters, with wire tied to them.
- Porcelain tubes. White tube ends sticking out about 1 cm where a wire passes through a joist.
- Two-prong outlets. If they were never converted, there's often K&T or early ungrounded wiring behind them.
- Cloth-wrapped wires in the basement or attic.
- An old panel fed by cloth-and-rubber-wrapped wires. FPE Stab-Lok panels often went in on top of K&T during 1970s upgrades.
What a rewire involves
For a typical Fairfield two-storey (about 2,000 sq. ft., 3 bedrooms, 1.5 baths):
- Assessment. After 80+ years of patches and suites, heritage homes are almost never all K&T. We find every K&T run so all of it gets replaced.
- Panel. Many K&T rewires include a panel upgrade, usually to 200A. See our panel upgrade article.
- Phased or full. If you're living there, we go one or two rooms at a time. An empty house, or one mid-renovation, gets done all at once for noticeably less.
- New wiring. New NMD90 (Loomex) cable fished through the walls, new boxes, outlets and switches, GFCI / AFCI per BCEC 2024.
- Permit and inspection. Permitted and inspected room by room or at completion.
- Insurance letter. A signed letter from the contractor that confirms no knob-and-tube remains in service. That's what your insurer wants.
What affects the cost
Square footage drives the cost, then the number of floors and how much protection and patching the finishes need (plaster costs more to work around than drywall). Every rewire is quoted after an on-site assessment. What moves the number:
| Home size | Notes |
|---|---|
| < 1,500 sq. ft. bungalow | Single floor, accessible attic, modest scope |
| 1,500 – 2,500 sq. ft. 2-storey | Typical Fairfield / James Bay heritage |
| 2,500+ sq. ft. heritage with finished basement | Larger Rockland homes; extensive finish restoration |
| Detached carriage or coach house (add-on) | Adds to the scope if included |
Phased work in an occupied home generally costs more than a full rewire in a vacant one. Many rewires also need a panel upgrade, plus permit fees.
How phasing works
An occupied rewire runs in four phases over 3–6 weeks:
- Panel and service. 1–2 days. The house switches to the new 200A service, with temporary kitchen and bath circuits.
- Main floor. 4–7 days. Kitchen, living room, dining room, main bathroom. This is the most disruptive week, and many people stay elsewhere.
- Upper floor. 3–5 days. Each bedroom opened, fished and patched.
- Basement / suite / finishes. 2–4 days. Cleanup, final inspection, walkthrough.
Power stays on room by room, except on panel-swap day.
What moves the price
1. Lath and plaster
Fishing through plaster is slower and patches are harder to hide. Plan on more labour, plus a heritage finisher to match the texture.
2. Condition of the existing wiring
All knob-and-tube comes out, no matter what shape it's in. Brittle wire insulation, runs buried in attic insulation and decades of patches all add time to the job.
3. Access
Attic access and an unfinished basement cost far less than cathedral ceilings and a finished suite, at the same square footage.
Book a heritage-home K&T assessment
An on-site assessment, a written scope, then a phased rewire quote. Book the assessment →
Dealing with your insurer
- Ask for one renewal. Some insurers will renew once with the K&T flagged while you arrange a rewire.
- Get a written quote from any TSBC-licensed contractor. That's often enough.
- Propose a schedule. Many insurers want a written commitment to rewire, often within 6–12 months.
- Send the completion letter. It confirms no knob-and-tube remains in service.
- Keep photos of the attic, basement and opened walls, before and after. We photograph as we go.
FAQ
The risk goes up when it's buried in insulation or feeding modern loads, but even K&T that looks intact has no ground and insulation that's 80 to 110 years old. It should all be replaced. If you're living with it in the meantime, don't run space heaters or other big loads on those circuits.
No. Every K&T circuit gets replaced with modern wiring. Old runs are pulled out where we can reach them and permanently disconnected where they're sealed inside finished walls, and the completion letter confirms no knob-and-tube is left in service.
Some disturbance can't be avoided. We put patches behind baseboard or crown, or in closets, and a heritage finisher matches the plaster, baseboards and floors to the era.
Not for K&T rewires specifically. Provincial rebates may cover part of some electrification upgrades for qualifying households.
Yes. K&T is a deal-killer for many CRD buyers, especially buyers who need a mortgage, since lenders require home insurance. A completed rewire with the contractor letter makes the house easier to insure and sell.
Sources & further reading
Insurance underwriting practices: Insurance Bureau of Canada and individual carrier underwriting guidelines. K&T renewal policy varies by insurer. Figures reflect underwriting seen on CRD heritage-home projects.
BC Hydro service-connection charges (when a rewire includes a service upgrade): bchydro.com.
Provincial rebates: betterhomesbc.ca.
Heritage scope & rewire cost factors: from Esteban Torres's work in the trade. Every home is different; we quote after an on-site assessment.
Keep reading
Why your Victoria panel might need an upgrade
Most K&T rewires include a panel upgrade. This covers what that part costs.
Read article BC Rebate ExplainersEV charger rebates in Victoria: what to know
Once the home is rewired, you can look at adding an EV charger.
Read article Service pagePanel upgrade & K&T service
What affects the cost, the process, and how we work in heritage homes.
View service